Image
Execution period 2008 - 2009
Contractor State Enterprise Radioactive waste

SITE APPROVAL FOR THE CONSTRUCTION OF NATIONAL RADIOACTIVE WASTE REPOSITORY

Risk Engineering Ltd. was the Contractor for Lot 4: “Feasibility Study, Updated Preliminary Analysis of the repository safety, and documentation set elaboration according to NRA requirements for site approval”. The task included the following:

  •  Technical analysis;
  •  Comprehensive comparative evaluation of alternative variants for construction;
  •  The technical options for implementation of the basic versions were analyzed, based on the conceptual elaborations and the technical solutions proposed.
  •  The economic assessment included as follows:
  •  Justification of the methods for general assessment of construction;
  •  Description and analysis of the different parameters influencing the economic assessment;
  •  Assessment of the analyzed options.
  •  Updated Preliminary Analysis of the repository safety was developed. In compliance with the requirements of the Regulation for the Procedure for Issuing Licenses and Permits for Safe Use of Nuclear Energy the following activities were completed:
  •  Updating of site data;
  •  Updating the technology of packages transportation;
  •  Updating the data on the insulation properties of barriers;
  •  Updating the data on the technology of disposal and repository insulation;
  •  Updating the radiation protection and surveillance area.
  •  A documentation set, necessary for filing the application for site approval by the NRA Chairman, was developed as required by Art. 37 of the Regulation for the Procedure for Issuing Licenses and Permits for Safe Use of Nuclear Energy.
  •  Analysis of the regulatory framework;
  •  Defining the necessary documents;
  •  Elaboration of a Site Monitoring Program;
  •  Elaboration of a Program for additional studies;
  •  Development of other necessary documents.
Back to all projects