Execution period 2008 - 2010
Contractor TPP Maritsa East 2 EAD

PROCUREMENT, DISMANTLING, MOUNTING AND COMMISSIONING OF WATER AND HYDROGEN COOLED GENERATORS

The engineering project for the total replacement of 210МW Generators by new ones of 230МW includes the following activities:

  •  Design related to Electrical, Machine and Process, Civil Structural, I&C Parts and drafting and submittal of full scope documentation for the equipment, installation plans, schedules, instructions etc.;
  •  Procurement of two generators and related equipment  for their replacement; dismantling the old equipment, preparation of the foundation for Generator No. 6 new equipment installation;
  •  Generator No. 6 installation, testing and startup, in accordance with the factory instructions and regulatory requirements.

The task performance requires constant coordination with the activities of other companies at the site and organization of the mutual activity of companies-subcontractors of Risk Engineering Ltd. Large scope of engineering tasks was solved including reconstruction and repair of all process systems related to generator’s operation.

The result is achieving Generator No.6 power increase by 20МW and reliable performance of the facility.