Execution period 2008 - 2011
Contractor Svilocel EAD

10.5МW TURBINE GENERATOR INSTALLATION AND COMMISSIONING, 6КV SWG REHABILITATION

The task includes:

  • new 10.5 MW turbine generator design and connection with the existing 6kV SWG, as well as cubicle retrofit with new breaker and relay protection installation;
  • procurement, installation and commissioning of a breaker, measuring transformers and relay protections of the generator;
  • electrometers procurement;
  • manual and automated synchronization of the generator to the transmission grid.

 